County Shoreland Zoning Permit in Kenosha County
Complete requirements, fees, and application details for obtaining a county shoreland zoning permit in Kenosha County, Wisconsin.
A county shoreland zoning permit in Kenosha County costs $200-$500. Processing takes 4-8 weeks. Contact the Kenosha County permit office to apply. One or more inspections are required.
This data was verified against official Kenosha County records as of 2026-01-15. Source: Kenosha County permit office (www.kenoshacounty.org/zoning).
Requirements
| Fee | $200-$500 |
| Processing Time | 4-8 weeks |
| Application | Contact permit office |
| Inspections Required | Yes |
| Contact | (262) 857-1895 |
| Office Hours | Mon–Fri 8:00 AM – 4:30 PM |
| Last Verified | 2026-01-15 |
How to Apply for a County Shoreland Zoning Permit in Kenosha County
- Determine requirements. Confirm that your project requires a county shoreland zoning permit by contacting the Kenosha County permit office at (262) 857-1895.
- Prepare documents. Gather required plans, specifications, contractor credentials, and any supporting documentation for your application.
- Submit application. Submit your application in person at 19600 75th St, Suite 185, Bristol, WI 53104. Check with the permit office for accepted document formats.
- Pay fees. The fee for a county shoreland zoning permit in Kenosha County is $200-$500. Fees are typically due at time of application.
- Await review. Processing typically takes 4-8 weeks. You will be notified when your permit is approved or if additional information is needed.
- Schedule inspections. Once your permit is approved and work begins, schedule required inspections at each construction milestone. Contact the permit office to arrange inspection times.
County Shoreland Zoning Permit in Other Jurisdictions
Frequently Asked Questions — County Shoreland Zoning Permit in Kenosha County
How much does a county shoreland zoning permit cost in Kenosha County?
A county shoreland zoning permit in Kenosha County costs $200-$500. Fees may vary based on project scope and valuation. Contact the Kenosha County permit office for an exact fee quote for your project.
How long does it take to get a county shoreland zoning permit in Kenosha County?
Processing time for a county shoreland zoning permit in Kenosha County is typically 4-8 weeks. Timelines depend on project complexity and current application volume. Plan submissions during off-peak periods may be processed faster.
How do I apply for a county shoreland zoning permit in Kenosha County?
Contact the Kenosha County permit office to submit your county shoreland zoning permit application. You will need project plans, contractor credentials, and the applicable fee. Check with the permit office for specific submission requirements and accepted formats.
What happens if I start work without a county shoreland zoning permit in Kenosha County?
Working without a required county shoreland zoning permit in Kenosha County can result in stop-work orders, fines, required removal of unpermitted work, and complications when selling the property. Always obtain the required permit before beginning work.
Managing permits across multiple jurisdictions?
Get fee changes, requirement updates, and deadline alerts for every municipality you work in. Built for contractors, expeditors, and compliance teams.