Fire Sprinkler System Permit in City of Green Bay
Complete requirements, fees, and application details for obtaining a fire sprinkler system permit in City of Green Bay, Wisconsin.
A fire sprinkler system permit in City of Green Bay costs $85 + $2 per head. Processing takes 1-2 weeks. Applications can be submitted online. One or more inspections are required.
This data was verified against official City of Green Bay records as of 2026-02-15. Source: City of Green Bay permit office (greenbaywi.gov/permits).
Requirements
| Fee | $85 + $2 per head |
| Processing Time | 1-2 weeks |
| Application | Apply online → |
| Inspections Required | Yes |
| Contact | (920) 448-3300 |
| Office Hours | Mon–Fri 8:00 AM – 4:30 PM |
| Last Verified | 2026-02-15 |
How to Apply for a Fire Sprinkler System Permit in City of Green Bay
- Determine requirements. Confirm that your project requires a fire sprinkler system permit by contacting the City of Green Bay permit office at (920) 448-3300.
- Prepare documents. Gather required plans, specifications, contractor credentials, and any supporting documentation for your application.
- Submit application. Apply online through the City of Green Bay online portal, or submit in person at 100 N Jefferson St, Room 608, Green Bay, WI 54301.
- Pay fees. The fee for a fire sprinkler system permit in City of Green Bay is $85 + $2 per head. Fees are typically due at time of application.
- Await review. Processing typically takes 1-2 weeks. You will be notified when your permit is approved or if additional information is needed.
- Schedule inspections. Once your permit is approved and work begins, schedule required inspections at each construction milestone. Contact the permit office to arrange inspection times.
Fire Sprinkler System Permit in Other Jurisdictions
Frequently Asked Questions — Fire Sprinkler System Permit in City of Green Bay
How much does a fire sprinkler system permit cost in City of Green Bay?
A fire sprinkler system permit in City of Green Bay costs $85 + $2 per head. Fees may vary based on project scope and valuation. Contact the City of Green Bay permit office for an exact fee quote for your project.
How long does it take to get a fire sprinkler system permit in City of Green Bay?
Processing time for a fire sprinkler system permit in City of Green Bay is typically 1-2 weeks. Timelines depend on project complexity and current application volume. Plan submissions during off-peak periods may be processed faster.
Can I apply for a fire sprinkler system permit online in City of Green Bay?
Yes. City of Green Bay accepts online permit applications. You can submit your fire sprinkler system permit application, upload required documents, and pay fees through the online portal.
What happens if I start work without a fire sprinkler system permit in City of Green Bay?
Working without a required fire sprinkler system permit in City of Green Bay can result in stop-work orders, fines, required removal of unpermitted work, and complications when selling the property. Always obtain the required permit before beginning work.
Managing permits across multiple jurisdictions?
Get fee changes, requirement updates, and deadline alerts for every municipality you work in. Built for contractors, expeditors, and compliance teams.